100,000 square feet

Associate Architect
The Sheward Partnership

Photography
Matt Wargo

LEED GOLD CERTIFIED

The new Commodore John Barry Elementary School accommodates 646 students from pre-kindergarten through 8th Grade on Philadelphia’s west side. The site is bounded on all four sides by 2 story brick row houses, dating to the early 1900’s.

 

The design challenge for this project was to provide a first rate academic facility on a gritty, tight urban site. To maximize outdoor play area and neighborhood green space, a four-story school was designed with minimal at grade play areas and roof gardens adjacent to 4th floor classrooms.

The schedule was a challenge for the project.  Design and Construction Documents were completed in 8 months and construction complete in 16 months.  The original schedule called design and construction to be completed in 3 years.  

The new school contains 46 classrooms. Additional instructional spaces include Art, Science, Vocal Music, and Technical Education.  The building contains a Cafetorium with a stage area and Warming Kitchen, a Gymnasium with locker and shower areas and an Instructional Media Center, containing a computer classroom, conference rooms and a library.  

Altres projectes per Ross Barney Architects

Lincoln Park Zoo, Searle Visitor Center
Chicago, USA
CTA Morgan Station
Chicago, IL, USA
McDonald’s Disney Flagship
Orlando, USA
UMD James I Swenson Civil Engineering Building
Duluth, MN, USA
JRC Synagogue
Evanston, IL, USA